315.472.5238
Services
315.472.5238
Home

Exit 33

JPSllp served as Geotechincal and Structural Engineer of Record for this 75,000sf addition to Turning Stone Resort and Casino.  This was fast track project in every sense, with total time from start of design to open lasting 10 months, including a complete re-design at month 3 and significant re-design at month 5.   A project highlight is a sound isolation system installed between the piano bar and rock-and-roll venue directly below.